Closed mgalloy closed 12 months ago
We can free up space in the various process.*
directories:
- [ ] 35G process.bilinear
- [ ] 1.3T process.centering-comparison
- [ ] 1001G process.commissioning-test
- [x] 139G process.commissioning-test-2
- [ ] 188G process.commissioning-test-3
- [ ] 176G process.commissioning-test-4
- [ ] 1.3G process.commissioning-test-5
- [ ] 44G process.diff-centering
- [ ] 391M process.fail-to-process
- [ ] 1.4G process.gbu-test
- [ ] 34G process.he-contsub
- [ ] 1.8T process.intermediate
- [ ] 78G process.l1-verification
- [x] 813G process.latest
- [x] 185G process.linewidth
- [ ] 37G process.no-badframes
- [ ] 59G process.nomask
- [ ] 55G process.offsets
- [ ] 84G process.publish
- [ ] 33G process.raw-chi2
- [ ] 6.6G process.rcam
- [ ] 29G process.regression
- [ ] 6.6G process.tcam
- [ ] 0 process.unit
- [ ] 264G process.wilson
- [x] 338G process.workshop
- [x] 122G process.workshop-test
6.7T total
We have 392 days with data that we are reprocessing. Currently it is all at version 0.5.0 (from the Workshop reprocessing) except for one day that I did as a test day for Don.
0.5.0: 391 days
0.5.1-dev: 1 day
I will report progress on the reprocessing in this issue.
Two servers were knocked out of the pool of processors for this reprocessing because they couldn't see the production database, but Tom S. was able to get them seeing it again. So we should have 8 servers with 2 processes (16 total processes) each running most of the time.
Started reprocess at approximately 3:50 pm on Wed Nov 22, 2023.
YEAH MIKE!
42 days finished after about 5 hours:
logs$ progress
Wed Nov 22 20:56:28 MST 2023
--L--: 12 days
0.5.0: 337 days
0.5.1-dev: 1 day
1.0.0: 42 days
That is fantastic!
Almost 17 hours in, and about 25% done:
$ progress
Thu Nov 23 08:39:15 MST 2023
--L--: 12 days
-----: 2 days
0.5.0: 280 days
1.0.0: 98 days
We are 30 hours in and 42% complete (predicting a finish on Saturday evening, but there are always a few stragglers at the end to clean up).
$ progress
Thu Nov 23 21:55:47 MST 2023
--L--: 15 days
-----: 2 days
0.5.0: 211 days
1.0.0: 164 days
We are about 40:40 into the reprocessing and 54% complete (still predicting a Saturday evening finish).
$ progress
Fri Nov 24 08:31:21 MST 2023
--L--: 13 days
-----: 3 days
0.5.0: 166 days
1.0.0: 210 days
We are 48 hours into the reprocessing and 60% complete (probably an early Sunday morning finish now).
$ progress
Fri Nov 24 15:51:05 MST 2023
--L--: 14 days
-----: 2 days
0.5.0: 142 days
1.0.0: 234 days
We are 53.5 hours into the reprocessing and 67% complete (probably an early Sunday morning finish).
$ progress
Fri Nov 24 21:14:03 MST 2023
--L--: 14 days
-----: 2 days
0.5.0: 115 days
1.0.0: 261 days
We are under 65 hours into the reprocessing and 80% complete (still projecting an early Sunday morning finish).
$ progress
Sat Nov 25 08:36:54 MST 2023
--L--: 11 days
-----: 2 days
0.5.0: 67 days
1.0.0: 312 days
We are just under 78.5 hours into the reprocessing and over 96% complete — we should finish just after midnight.
$ progress
Sat Nov 25 22:15:20 MST 2023
--L--: 6 days
-----: 2 days
0.5.0: 6 days
1.0.0: 378 days
We are basically done, just picking up a couple of stragglers:
$ progress
Sun Nov 26 08:35:12 MST 2023
--L--: 1 day
-----: 2 days
0.5.0: 1 day
1.0.0: 388 days
For some reason, 20220524 and 20220525 are not marked done in the database, but logs show they processed without error. They don't have much data, but there are some science files processed. 20210821 is almost done and then 20210822 will be processed when that is done.
The missing versions on 20220524 and 20220525 are from this:
# From issue #159: "the Cropico battery died, and all temps were misreported as
# being ~4C too low. This looks to get bad 20220523.212656.81.ucomp.789.l0.fts
# and remains bad for the rest of the day. We didn't collect UCoMP data again
# until the 30th, and the problem was resolved on the 25th.
[20220523.212656]
process : NO
[20220530]
process : YES
The last day finished around 10:50 am this morning (91 hours total, but almost all days were done last night after 78 hours or so).
Started fixing up the database plots at 11:24 am on Sunday 26 November 2023.
Started reprocessing with version 1.0.01 at 4:05 pm on Wednesday 29 November 2023.
We are nearly 5 hours into the reprocessing and just under 7% complete.
$ progress
Wed Nov 29 21:57:47 MST 2023
--L--: 13 days
-----: 2 days
1.0.0: 350 days
1.0.1: 27 days
We are just over 16 hours into the 1.0.1 reprocessing and about 18.5% complete (projected Sunday morning finish).
$ progress
Thu Nov 30 08:17:08 MST 2023
--L--: 15 days
-----: 2 days
1.0.0: 302 days
1.0.1: 73 days
I've updated my progress
script:
$ progress
Thu Nov 30 21:49:08 MST 2023 (running for 29 hours)
--L--: 11 days
-----: 2 days
1.0.0: 233 days
1.0.1: 146 days
estimated completion time: Sat Dec 2 23:54:00 MST 2023
$ progress
Fri Dec 1 07:52:26 MST 2023 (running for 39 hours)
--L--: 8 days
-----: 2 days
1.0.0: 201 days
1.0.1: 181 days
estimated completion time: Sun Dec 3 06:14:00 MST 2023
$ progress
Fri Dec 1 21:49:02 MST 2023 (64% complete, running for 53 hours)
estimated completion time: Sun Dec 3 03:40:00 MST 2023
--L--: 16 days
-----: 2 days
1.0.0: 124 days
1.0.1: 250 days
$ progress
Sat Dec 2 07:20:21 MST 2023 (75% complete, running for 63 hours)
estimated completion time: Sun Dec 3 03:50:00 MST 2023
--L--: 12 days
-----: 2 days
1.0.0: 84 days
1.0.1: 294 day
$ progress
Sat Dec 2 22:19:32 MST 2023 (93% complete, running for 78 hours)
estimated completion time: Sun Dec 3 04:06:00 MST 2023
--L--: 9 days
-----: 2 days
1.0.0: 18 days
1.0.1: 363 days
We are done with the 1.0.1 reprocessing. Now, I will start the jobs for fixing up the plots from the database for #164.
Reprocess the data and publish the data on the web.
Need to start this by November 22, 2023 to give enough to time, with a buffer to complete by AGU.
Reprocess 20210715 until the cameras were changed in November 2022.
Tasks
ucomp-config