Upload available cable route shapefiles with background information such as when it can be updated and who may have access.
This task was created in response to a conversation with Anna Mercer, Lianne Allen-Jacobson, Greg Ardini, and Marina Chaji on March 2nd about scallopers' willingness to finish in wind development areas.
The buried cable route from a WEA to shore is likely to be closed as well. Cable buried at shallow depths and marked with concrete.
Scallop dredging will not be possible in areas where buried cables running from the shore out to the #turbines are located.
Vessel operators will not want to risk damaging their gear by dredging too close to these areas; we estimate that operators will avoid dredging within 0.5nm of any buried cables.
The location of the cables can be extracted from construction operations plans.
Upload available cable route shapefiles with background information such as when it can be updated and who may have access.