Closed Storwars closed 4 months ago
@Storwars, thanks for your feedback. We'll investigate and update you here.
@Storwars thanks for your feedback. In step 10 of procedure where the ports are shut down on the switch, this action will cause the LIFs to fail over to the other switch. A manual revert is not needed.
Page URL
https://docs.netapp.com/us-en/ontap-systems-switches/switch-nvidia-sn2100/migrate-cn1610-sn2100-cluster-switch.html
Page title
Migrate CN1610 cluster switches to NVIDIA SN2100 cluster switches
Summary
I might be wrong but I fail to see the interface revert procedure between the replacement of the first and second switches. Since auto revert is disable (per procedure early step), if we move from replacing cl2 to cl1 without manually reverting the first LIFS, we'll be in a bad place.