The tool is designed for industrial energy coordinators, plant managers, engineers, and personnel who are interested in improving system efficiency to help them benchmark, baseline, and visualize their energy and utility bills and use.
Revising Issue #531: Model data set to zero. If modeled energy use is less than zero, override to zero
Instead if ADJUSTED BASELINE (Adjusted for normalization + baseline adjustment) then override to zero.
Watch out for "% savings" I think it is calculated as "Savings / adjustedBaseline" so may need a catch to keep infinity from appearing :)
Modeled energy use CAN be < 0
Talk to Chris/Kris before implementing. Chris may have changed his mind about modeled energy
Revising Issue #531: Model data set to zero. If modeled energy use is less than zero, override to zero
Instead if ADJUSTED BASELINE (Adjusted for normalization + baseline adjustment) then override to zero. Watch out for "% savings" I think it is calculated as "Savings / adjustedBaseline" so may need a catch to keep infinity from appearing :)
Modeled energy use CAN be < 0