Open bruno-g opened 2 years ago
I can see that this is a problem for the simulation developer/maintainer, but I don't see why it is a problem for C2SIM.
Seems to be an implementation question.
Mark
bruno-g wrote on 6/9/22 12:21 PM:
Submitter Organization: NMSG-145 (Operationalization of Standardized C2-Simulation Interoperability)
Type (Problem Report or Change Request): Problem Report Date of Submission: 9 June 2022 Product: C2SIM 1.0.0/1.0.1 + SMX + LOX ontologies (rdf/xml)
Reference: NMSG-145 Final Report / Technical report TR-MSG-145, April 2021, Section 3.1.3.3, p46 (3-6)
Problem/Change Description: [...] 3.1 USE CASE DESCRIPTION AND IMPLEMENTATION [...] 3.1.3 Mission Planning for Army (Norway) [...] 3.1.3.3 Experimentation [The cadets] wanted the simulation speed to run much faster, and the ability to change the speed during the simulation. [The cadets] also wanted to stop the simulation, make decisions and possibly changes to the plan, and then continue from current state.
— Reply to this email directly, view it on GitHub https://github.com/OpenC2SIM/C2SIMArtifacts/issues/24, or unsubscribe https://github.com/notifications/unsubscribe-auth/ABN7HSMUF3ZHTGOVWJOPLVTVOHATFANCNFSM5YJRI5DA. You are receiving this because you are subscribed to this thread.Message ID: @.***>
A C2SIM command to set simulation rate was used in the 2022 CWIX (Coalition Warrior Interoperability Exercise) -- see Issue #3. Also a command to pause and continue simulation execution. Resolution of Issue #3 may address all that is needed to resolve Issue #24.
Information on this and related issues (3, 6, 36) sent to the SISO PDG/PSG reflector for feedback/discussion on 11/1/2022 in preparation for subsequent e-vote by the C2SIM community.
XML schema in support of CWIX 2023 was generated for the merged Core-SMX-LOX ontology on 1 February 2023, to include the change for this issue.
C2SIM Problem Report / Change Request Submitter Organization: NMSG-145 (Operationalization of Standardized C2-Simulation Interoperability) Date of Submission: 9 June 2022 Type (Problem Report or Change Request): Problem Report Product: C2SIM 1.0.0/1.0.1 + SMX + LOX ontologies (rdf/xml)
Reference: NMSG-145 Final Report / Technical report TR-MSG-145, April 2021, Section 3.1.3.3, p46 (3-6)
Problem/Change Description: [...] 3.1 USE CASE DESCRIPTION AND IMPLEMENTATION [...] 3.1.3 Mission Planning for Army (Norway) [...] 3.1.3.3 Experimentation [The cadets] wanted the simulation speed to run much faster, and the ability to change the speed during the simulation. [The cadets] also wanted to stop the simulation, make decisions and possibly changes to the plan, and then continue from current state.