Thanks Ryan. We need to hit that June date for our foundation plan. On Jun 8, 2015 5:26 PM, "Ryan Schultz" notifications@github.com wrote:
@andyeck1 https://github.com/andyeck1,
Do you have an anticipated time frame that you'll have permit drawings?
We'll most likely entertain the 'Permission to Start' & 'Footing & Foundation Plans Only' http://dsps.wi.gov/Documents/Industry%20Services/Forms/Commercial%20Buildings/SB-Form118App.pdf options for state review.
@Kraut34 https://github.com/Kraut34, per the following link (which gets updated regularly) the next available date for review for (4 COMMERCIAL BLDGS - STANDARD (TYPE: ALL OTHERS, 3 OR LESS FLOORS) is on 06-24-2015 http://apps2.commerce.wi.gov/SB_PlbgPlanReviewApp/report.html
I'm unsure (I will call tomorrow) whether a 'Permission to Start' review can be submitted any early.
Regardless, they indicate via their FAQs http://dsps.wi.gov/Documents/Industry%20Services/Forms/Plan%20Review/COMMERCIAL%20PLAN%20REVIEW%20FREQUENTLY%20ASKED%20QUESTIONS2014.pdf, they turn around plans in 15 business days. Again, not sure if this is accelerated for 'Permission to Start' applications. Will ask.
Regardless, for OpeningDesign's ARCH scope, we around about 3 or 4 weeks out for permit drawings.
Thanks, Ryan
— Reply to this email directly or view it on GitHub https://github.com/OpeningDesign/Sports_Complex/issues/46.
When are the final reactions going to be issued?
Thank you, Andy Eck Ntrive 630-318-1725 Sent from my iPhone
On Jun 8, 2015, at 5:31 PM, kraut34 notifications@github.com wrote:
Thanks Ryan. We need to hit that June date for our foundation plan. On Jun 8, 2015 5:26 PM, "Ryan Schultz" notifications@github.com wrote:
@andyeck1 https://github.com/andyeck1,
Do you have an anticipated time frame that you'll have permit drawings?
We'll most likely entertain the 'Permission to Start' & 'Footing & Foundation Plans Only' http://dsps.wi.gov/Documents/Industry%20Services/Forms/Commercial%20Buildings/SB-Form118App.pdf options for state review.
@Kraut34 https://github.com/Kraut34, per the following link (which gets updated regularly) the next available date for review for (4 COMMERCIAL BLDGS - STANDARD (TYPE: ALL OTHERS, 3 OR LESS FLOORS) is on 06-24-2015 http://apps2.commerce.wi.gov/SB_PlbgPlanReviewApp/report.html
I'm unsure (I will call tomorrow) whether a 'Permission to Start' review can be submitted any early.
Regardless, they indicate via their FAQs http://dsps.wi.gov/Documents/Industry%20Services/Forms/Plan%20Review/COMMERCIAL%20PLAN%20REVIEW%20FREQUENTLY%20ASKED%20QUESTIONS2014.pdf, they turn around plans in 15 business days. Again, not sure if this is accelerated for 'Permission to Start' applications. Will ask.
Regardless, for OpeningDesign's ARCH scope, we around about 3 or 4 weeks out for permit drawings.
Thanks, Ryan
— Reply to this email directly or view it on GitHub https://github.com/OpeningDesign/Sports_Complex/issues/46.
— Reply to this email directly or view it on GitHub.
I know they're asking for resolution on #41 before they finalize their reactions.
@kraut34, Here's the footing and foundation plans/specs sent to the state: https://github.com/OpeningDesign/Sports_Complex/blob/20deff1783030452bc4afa26abf58024e2ba4db1/Transfer/20150708%20-%20Foundation%20Permit%20Set%20sent%20to%20State/Sent%20to%20GC/20150104_150708_Sports%20Complex%20Drawings%20and%20Specs%20.pdf
@andyeck1,
Do you have an anticipated time frame that you'll have permit drawings?
We'll most likely entertain the 'Permission to Start' & 'Footing & Foundation Plans Only' options for state review.
@Kraut34, per the following link (which gets updated regularly) the next available date for review for (4 COMMERCIAL BLDGS - STANDARD (TYPE: ALL OTHERS, 3 OR LESS FLOORS) is on 06-24-2015 http://apps2.commerce.wi.gov/SB_PlbgPlanReviewApp/report.html
I'm unsure (I will call tomorrow) whether a 'Permission to Start' review can be submitted any early.
Regardless, they indicate via their FAQs, they turn around plans in 15 business days. Again, not sure if this is accelerated for 'Permission to Start' applications. Will ask.
Regardless, for OpeningDesign's ARCH scope, we around about 3 or 4 weeks out for permit drawings.
Thanks, Ryan