Closed ct-martin closed 5 years ago
What is the next step to move this forward?
@jwflory I'd like to know if Ian does find anything as per #72, and then I need to write Mr. Mezziazini an email to with out times.
I have info now, need to email Dr. Skuse to see what his schedule looks like
Forgot to update the issue. We have a time this week and three of us will be heading down. @jrtechs will help with server setup and @icflournoy will help with networking
Dr. Skuse was unavailable during the time we were going to visit the CBET machines. We have since rescheduled, and are planning on sending him a secondary reminder a day or two before the meeting.
@ct-martin are you guys going in tomorrow (Thursday) to visit the CBET machines? If so, we should send Dr. Skuse an email as a reminder.
This was completed this week. @ct-martin, is there anything remaining before this is closed out?
We got some stuff running and online from trip 3.
@ct-martin will write a follow up email with Dr. Skuse.
TLDR work on CBET trip # 4
@ct-martin I know you're busy this week, but whenever you have time, just let us know if there's anything remaining from trip # 3 keeping us from closing this issue :+1:
@Tjzabel it's just the write-up, but I'm totally buried right now
@ct-martin all good :+1: Just wanted to know where we were at with progress on that.
TL;DR (not proper write-up):
@ct-martin are we free to close this issue? I'm not sure what we need to do to close this out.
@Tjzabel I need to document passwords, will look at in an hour
RITlug GitLab is down, will post when back up
Passwords were added to creds (private) repo; closing this issue
Schedule another trip to the CBET datacenter to try to finish setting up the servers.