RITlug / tasks

Real-life issue tracker for tasks, goals, and objectives for RITlug
https://ritlug.com
Creative Commons Attribution Share Alike 4.0 International
6 stars 1 forks source link

Order new power cables for Titan and new R900 #125

Open Tjzabel opened 5 years ago

Tjzabel commented 5 years ago

It has come to our attention that Titan requires a new power cable, and the new R900 we installed also requires another cable.

Nathan Felton, our contact in the datacenter, recommended we get 3-4 of these cables in 1-2 feet lengths.

nlMeminger commented 5 years ago

When are these cables needed?

On Fri, Aug 23, 2019 at 14:13 Tim Zabel notifications@github.com wrote:

Assigned #125 https://github.com/RITlug/tasks/issues/125 to @nlMeminger https://github.com/nlMeminger.

— You are receiving this because you were assigned.

Reply to this email directly, view it on GitHub https://github.com/RITlug/tasks/issues/125?email_source=notifications&email_token=AELFBEPJK7YILVNWA2NH2GDQGASFJA5CNFSM4IPCDQ72YY3PNVWWK3TUL52HS4DFWZEXG43VMVCXMZLOORHG65DJMZUWGYLUNFXW5KTDN5WW2ZLOORPWSZGOTHHNK5A#event-2580469108, or mute the thread https://github.com/notifications/unsubscribe-auth/AELFBEJNNYHW7KNTUNBOCODQGASFJANCNFSM4IPCDQ7Q .

Tjzabel commented 5 years ago

These aren't needed by any specific time, just soon-ish (within a couple weeks).

This'll be a good first task to complete as treasurer. This will require going to the club office and ordering these cables with their credit card.

jrtechs commented 5 years ago

Before @nlMeminger can do that he needs to complete RIT's financial training. https://www.rit.edu/studentaffairs/campuslife/financial-certification-test

nlMeminger commented 5 years ago

Can do probably tomorrow

On Sat, Aug 24, 2019 at 09:04 Jeffery Russell notifications@github.com wrote:

Before @nlMeminger https://github.com/nlMeminger can do that he needs to complete RIT's financial training. https://www.rit.edu/studentaffairs/campuslife/financial-certification-test

— You are receiving this because you were mentioned.

Reply to this email directly, view it on GitHub https://github.com/RITlug/tasks/issues/125?email_source=notifications&email_token=AELFBEJEJZLVY3FWGKUJ4ITQGEWVNA5CNFSM4IPCDQ72YY3PNVWWK3TUL52HS4DFVREXG43VMVBW63LNMVXHJKTDN5WW2ZLOORPWSZGOD5B7UIY#issuecomment-524548643, or mute the thread https://github.com/notifications/unsubscribe-auth/AELFBEMVF2YGO36DDDOUWPLQGEWVNANCNFSM4IPCDQ7Q .

Tjzabel commented 5 years ago

@jrtechs good catch!

Tjzabel commented 5 years ago

@jrtechs so the financial training is live? That's good to know.

Tjzabel commented 5 years ago

Since I've completed the financial training, I can take a look at ordering these today.

jrtechs commented 4 years ago

Last time I checked the EAF is still pending for the order of the power cable. @nlMeminger, @Tjzabel, can you two look into this to see why the EAF got rejected/sent to limbo.

hkeena98 commented 4 years ago

1/13/2019

Tjzabel commented 4 years ago

EAF has been submitted.

nlMeminger commented 4 years ago

Ap proud of you, Tim

On Wed, Feb 26, 2020 at 12:09 Tim Zabel notifications@github.com wrote:

EAF has been submitted.

— You are receiving this because you were mentioned. Reply to this email directly, view it on GitHub https://github.com/RITlug/tasks/issues/125?email_source=notifications&email_token=AELFBELBNJIA426HHMOH54DRE2O35A5CNFSM4IPCDQ72YY3PNVWWK3TUL52HS4DFVREXG43VMVBW63LNMVXHJKTDN5WW2ZLOORPWSZGOENBCIFI#issuecomment-591537173, or unsubscribe https://github.com/notifications/unsubscribe-auth/AELFBEL5BVEHLYAFQGGF3RTRE2O35ANCNFSM4IPCDQ7Q .

Tjzabel commented 3 years ago

This should get taken care of in early fall 2021.