review milestone document #8

Closed sebmarste closed 6 years ago

sebmarste commented 6 years ago

presentation deck deadline is one week before presentation risk assessment by next Tuesday March 6 project architecture by next Tuesday March 6

  1. please make the spreadsheet version of the milestone doc available so we can follow the progress of your plan
  2. item 3.1: what is self-speaking naming schema?
  3. it is unclear what is the difference between the goals in task 3 and subtask 5.1
  4. Four days is a very long time for preparing a 35 minutes presentation. we recommend to focus on the project more and less about the presentation.
  5. item 5.3 is duration stated correctly?
  6. task 4 seems to take 12 days, you sure you need that much time for creating a simple web app?