Having a hard time finding much documentation and wanted to make sure the behavior I am experiencing is as designed.
Project: edit project start and end date
No impact to child milestones nor tasks
Milestone: edit end date on milestone
No impact to Project start nor end dates.
No impact to children of this milestone.
All subsequent milestones and their children moved out.
Task: edit end date
No impact to Project start nor end dates.
No impact to parent milestone.
Subsequent sibling tasks moved out.
No impact to subsequent milestones nor their children.
Gant: Click Project Config, enter 25 days excluding weekend work.
Changed Project end date.
No impact to milestones nor their children.
Having a hard time finding much documentation and wanted to make sure the behavior I am experiencing is as designed.
Project: edit project start and end date No impact to child milestones nor tasks
Milestone: edit end date on milestone No impact to Project start nor end dates. No impact to children of this milestone. All subsequent milestones and their children moved out.
Task: edit end date No impact to Project start nor end dates. No impact to parent milestone. Subsequent sibling tasks moved out. No impact to subsequent milestones nor their children.
Gant: Click Project Config, enter 25 days excluding weekend work. Changed Project end date. No impact to milestones nor their children.