Project > Milestone > Task Relationships #123

Open cjsigler opened 9 years ago

cjsigler commented 9 years ago

Having a hard time finding much documentation and wanted to make sure the behavior I am experiencing is as designed.

Project: edit project start and end date No impact to child milestones nor tasks

Milestone: edit end date on milestone No impact to Project start nor end dates. No impact to children of this milestone. All subsequent milestones and their children moved out.

Task: edit end date No impact to Project start nor end dates. No impact to parent milestone. Subsequent sibling tasks moved out. No impact to subsequent milestones nor their children.

Gant: Click Project Config, enter 25 days excluding weekend work. Changed Project end date. No impact to milestones nor their children.