Work Description
Describe the work done in detail:
In this task, I was able to effectively extract key information for the use case description. Overall the task was successful as I managed to complete the use case description with the right information.
The completion deadline for the project remains unchanged. This phase of work was planned and executed within the allocated time frame which aligns with the overall project schedule and does not need to be committed to the repository.
Start Date: 19/9/2023 End Date 21/9/2023
Description of task: This task involves providing the accurate capturing of the functional requirements and description of any interaction with the software for UC-1 to UC-3.
Goal of task: The task aims to provide a written description of how actors will be able to perform tasks on the application. It will capture all possible steps a user can take to perform the respective tasks.
Success of the task is dependent on the accurate description and capturing of the functionalities of use cases UC-1 to UC-3.
Allocated time: 2 days
Start Date: 19/9/2023 End Date: 21/9/2023
Owner: Zi bin Status: Completed
Priority: High