Create a comprehensive project schedule for your term project using a project scheduling tool. This includes Microsoft Project, Ganttproject, ProjectLibre, any other program or SAAS scheduling tool. A spreadsheet is not an acceptable scheduling tool!
[ ] Start at the beginning of the term.
[ ] Mark tasks that are complete if possible.
[ ] Use hierarchy and concurrent engineering, and adhere to the guidelines for schedules as described in class (tasks 5 days or less, succinctly described, etc).
[ ] Tasks must have dependencies, and you should think about adding sprints if you're doing sprints, or "phases" if not.
[ ] Make sure your schedule has been reviewed in a team meeting and that all project team members have approved it.
[ ] Extra credit: Add your team as resources. Try to perform balancing and load-leveling.
[ ] Post the schedule to your collab site and upload it as a PDF to Canvas.
[ ] Be sure to identify the project management application you're using.
Create a comprehensive project schedule for your term project using a project scheduling tool. This includes Microsoft Project, Ganttproject, ProjectLibre, any other program or SAAS scheduling tool. A spreadsheet is not an acceptable scheduling tool!
[ ] Start at the beginning of the term.
[ ] Mark tasks that are complete if possible.
[ ] Use hierarchy and concurrent engineering, and adhere to the guidelines for schedules as described in class (tasks 5 days or less, succinctly described, etc).
[ ] Tasks must have dependencies, and you should think about adding sprints if you're doing sprints, or "phases" if not.
[ ] Make sure your schedule has been reviewed in a team meeting and that all project team members have approved it.
[ ] Extra credit: Add your team as resources. Try to perform balancing and load-leveling.
[ ] Post the schedule to your collab site and upload it as a PDF to Canvas.
[ ] Be sure to identify the project management application you're using.