Unfortunately, I cannot get org-gtd to work properly in regards to automatically changing to the next todo in projects.
My steps (doom user):
Create a new project with a few tasks
First task is set to NEXT, others are set to TODO
I open "org-gtd-engage" and see the first job of the project as "NEXT"
I hit "t d" to set it to DONE
I expect the entry to disappear and the next todo of that project to appear carrying the NEXT status
What happens instead:
Entry is set to DONE but nothing else happens
I tried to downgrade from emacs 30 to 29. I reinstalled all packages. I played around with org-edna-mode and org-gtd-mode. Every combination of option seems to not work for me.
Hello there,
Unfortunately, I cannot get org-gtd to work properly in regards to automatically changing to the next todo in projects.
My steps (doom user):
What happens instead:
I tried to downgrade from emacs 30 to 29. I reinstalled all packages. I played around with org-edna-mode and org-gtd-mode. Every combination of option seems to not work for me.
Any help or suggestion is highly appreciated.