The Guest House at the 125 Frederick property currently receives electrical power through a shared service panel that is rated at 100 amps. In order to accommodate the increased energy demands and enhance the reliability of the electrical supply, an upgrade to a dedicated 100 amps sub-panel sourced from the newly proposed 400 amps 4 gangs service panel is necessitated. This sub-panel will ensure that the Guest House has an independent and stable power supply, mitigating any potential overload issues and aligning with modern electrical standards.
Tasks
Design and Documentation
Create a detailed design for the Guest House sub-panel integration within the 400 amps service panel infrastructure.
Document the specifications and requirements for the dedicated 100 amps sub-panel.
Procurement of Materials
Acquire a 100 amps sub-panel with appropriate circuit breakers and safety devices.
Obtain all necessary wiring and ancillary components for the installation.
Installation
Install the 100 amps sub-panel in the Guest House, ensuring it occupies one gang within the 400 amps service panel.
Execute all necessary wiring and connections between the main service panel and the Guest House sub-panel.
Testing and Validation
Conduct thorough testing to verify the operational integrity of the sub-panel.
Validate that the power supply to the Guest House is consistent and meets the required specifications.
Documentation and Reporting
Compile a detailed report of the installation process, including diagrams and specifications.
Update the property's electrical system blueprints to reflect the new sub-panel installation.
Acceptance Criteria
The Guest House is equipped with a fully functional 100 amps sub-panel, occupying one gang in the 400 amps service panel.
The installation adheres to all applicable electrical codes and standards.
The power supply to the Guest House is stable and meets the designed specifications.
All testing and validation processes are documented, with the installation passing necessary inspections.
A comprehensive report, including updated blueprints and compliance certifications, is submitted.
Labels
Electrical
GuestHouse
SubPanel
DedicatedSupply
SafetyCompliance
Story Points
5 (Reflects the complexity and effort required for the installation and commissioning of the Guest House sub-panel.)
This description is intended to encapsulate the specific requirements and scope for the Guest House sub-panel installation. Any further considerations or adjustments that may arise should be communicated in a timely manner to ensure seamless integration into the overarching project plan.
Background
The Guest House at the 125 Frederick property currently receives electrical power through a shared service panel that is rated at 100 amps. In order to accommodate the increased energy demands and enhance the reliability of the electrical supply, an upgrade to a dedicated 100 amps sub-panel sourced from the newly proposed 400 amps 4 gangs service panel is necessitated. This sub-panel will ensure that the Guest House has an independent and stable power supply, mitigating any potential overload issues and aligning with modern electrical standards.
Tasks
Acceptance Criteria
Labels
Electrical
GuestHouse
SubPanel
DedicatedSupply
SafetyCompliance
Story Points