Execution of Electrical Panel Relocation #23

Open SuzyQuant opened 3 weeks ago

SuzyQuant commented 3 weeks ago

Objective:

This task involves the complete relocation of the electrical panel box from its current indoor location to a designated outdoor location based on the plan achieved from the Issue https://github.com/United-Home/2405-45th-St/issues/16, ensuring compliance with safety standards and local regulations.

Sub-tasks:

  1. Disconnect Power: Safely disconnect power to the existing electrical panel to prevent any electrical hazards during the relocation process.
  2. Remove Existing Panel: Carefully remove the existing electrical panel box from its current location, ensuring that all connections are properly detached.
  3. Install New Panel: Install the new electrical panel box at the designated outdoor location, ensuring secure mounting and accessibility.
  4. Connect Circuits: Reconnect all circuits to the new panel according to the previously developed circuit distribution plan from Issue https://github.com/United-Home/2405-45th-St/issues/15, ensuring proper organization and functionality.
  5. Test Functionality: Conduct thorough testing of the new panel to ensure all connections are operational and meet safety standards.

Acceptance Criteria: