Background
The porch at 313 Walnut is undergoing a significant transformation. As part of this process, a detailed preparation for professional painting is required. This task involves the removal of any remaining flaky paint, the repair of any damaged areas, and the application of caulking where necessary. This task is critical to ensure a smooth and ready surface for painting, contributing to the overall aesthetic and value of the property.
Specific and Detailed Tasks
[ ] Removal of Remaining Flaky Paint: Utilize a paint scraper or power washer to remove any remaining flaky paint from all surfaces of the porch. This task is crucial to ensure a smooth surface for painting. Estimated Time: 1 day
[ ] Repair of Damaged Areas: Identify and repair any damaged areas, including the window trimmings and the wood holding the glass of the French window. This task will ensure the integrity of the porch structure and improve the overall appearance. Estimated Time: 1-2 days
[ ] Application of Caulking: Apply caulking to the window trimmings and any other areas that require it. This task will ensure a tight seal and smooth surface for painting. Estimated Time: 1-2 days
Acceptance Criteria
All surfaces of the porch are free from flaky paint and are smooth, ready for painting.
All damaged areas, including the window trimmings and the wood holding the glass of the French window, are repaired.
Caulking is applied to the window trimmings and any other areas that require it, ensuring a tight seal and smooth surface for painting.
Story Points
This task is estimated to be a 5 on the Fibonacci scale (1, 2, 3, 5, 8, 13) of story points, considering the complexity, the amount of work, and the potential for unknowns.
Estimated Time
The total estimated time for this task is 3-5 days, with each specific task taking 1-2 days. This estimate includes time for potential unforeseen challenges that may arise during the process.
Background The porch at 313 Walnut is undergoing a significant transformation. As part of this process, a detailed preparation for professional painting is required. This task involves the removal of any remaining flaky paint, the repair of any damaged areas, and the application of caulking where necessary. This task is critical to ensure a smooth and ready surface for painting, contributing to the overall aesthetic and value of the property.
Specific and Detailed Tasks
Acceptance Criteria
Story Points This task is estimated to be a 5 on the Fibonacci scale (1, 2, 3, 5, 8, 13) of story points, considering the complexity, the amount of work, and the potential for unknowns.
Estimated Time The total estimated time for this task is 3-5 days, with each specific task taking 1-2 days. This estimate includes time for potential unforeseen challenges that may arise during the process.