Closed name54321 closed 11 months ago
Work Done: [3.1], [3.2], [3.3], [3.4], [3.5], [3.6], [3.7] completed
Committed to Repo: NA
Completion Dateline Affected: N
Changes to Success/Completion Criteria: N
Start/End Date of Update Work: 16/10/23 - 26/10/23
Description:
Task ID: 3
Task Detail: Design and create all the needed diagrams, updating of use case and requirements, and M2 Presentation
Task Goals: Three diagram, updated use case and requirements and presentation.
Success/Completion Criteria: When everything is completed
Allocated Time: 18 Day
Start/End Date: 16/10/23 - 08/11/23
Owner:
Zining, Victor, Jessaryn -> [3.1] All -> [3.2] Calvin -> [3.3], [3.4] Zining -> [3.5] All -> [3.6] Zining, Jessaryn -> [3.7] Zining, Calvin, Victor -> [3.8]
Task Status: Completed
Task Priority: Medium