If CTVs are always on site, the total duration of all activities should be equal to the simulation period. This isn't the case. Comparing the cumulative CTV activity duration and the env_time, it looks like the CTV is allowing 2x each weather delay to elapse before it tries to do anything. This also appears to be true for vessels that are not always on site.
If CTVs are always on site, the total duration of all activities should be equal to the simulation period. This isn't the case. Comparing the cumulative CTV activity duration and the env_time, it looks like the CTV is allowing 2x each weather delay to elapse before it tries to do anything. This also appears to be true for vessels that are not always on site.