Our team created for you one of the most innovative CRM systems that supports mainly business processes and allows for customization according to your needs. Be ahead of your competition and implement YetiForce!
Hello all, im new here and i need a little j\help if is possible.
I use YetiForce 5.1.0, and i have created a Project, on this project i have created 2 mile Milesones, in one milestone i have created 6 Task, 4 task have are complited and 2 not, now my problem is, why the Progres % is not calculate ? On the project i have 0% Progress.
Please help me if is possible.
Thank You
Hello all, im new here and i need a little j\help if is possible. I use YetiForce 5.1.0, and i have created a Project, on this project i have created 2 mile Milesones, in one milestone i have created 6 Task, 4 task have are complited and 2 not, now my problem is, why the Progres % is not calculate ? On the project i have 0% Progress. Please help me if is possible. Thank You