Invalid date for event can be accepted by the program #5

Open Zhengwinter opened 4 months ago

Zhengwinter commented 4 months ago

image.png

If a user enters an invalid date, I'm using "00" as the day, the system still accepts the event and adds it to the calendar. This can be problematic especially if the user accidentally typed in an erroneous date and it was accepted, and checking back, the user forgets which date he/she was supposed to add.

soc-pe-bot commented 4 months ago

Team's Response

This has been mentioned in the UG Q&A Section.

image.png

Items for the Tester to Verify

:question: Issue response

Team chose [response.NotInScope]

Reason for disagreement: The developer team does not seem to be addressing the issue that I am pointing out.

I am pointing out the fact that the program accepts invalid dates like a date with "00" as the day.