Closed poh-zun closed 1 year ago
Drafting and refining of all functional requirements for IT Administrator completed. There are a total of 5 requirements for staff: FR18 to FR22
Work was not committed to the repository.
Progress does not affect the deadline.
No changes to the criteria/success of the task.
Start Date: 7th September 2023 End Date: 11th September 2023
High Priority
To further refine M1 Report section - Functional Requirements for IT Administrator
Objective
Success Criteria
Start Date: 7th September 2023 End Date: 11th September 2023 Allocated Time: 3 days