Closed Cherlin01 closed 12 months ago
Product Overview drafted out in M1 Report document by Cherlin. Product Overview captured the high level functionality of the system.
Work was not committed to the repository.
Progress does not affect the deadline.
No changes to the criteria/success of the task.
Start Date: 5th September 2023 End Date: 7th September 2023
Medium Priority
To write up M1 Report section - Product Overview
Objective
Draft out product overview Success Criteria
The product overview should capture the high level functionality of the system.
Start Date: 5th September 2023 End Date: 7th September 2023 Allocated Time: 3 days