Closed aloysiustayy closed 1 year ago
Completion of drafting and refining Use Case Descriptions of all 3 Actors, along with the Use Case ID after refinement of Use Case Diagrams. Use Case Descriptions matches Use Case Diagrams.
Work was not committed to the repository.
Progress does not affect the deadline.
No changes to the criteria/success of the task.
Start Date: 15th September 2023 End Date: 20th September 2023
High Priority
M1 Report Section - Appendix A - Use Case Descriptions (IT Administrator)
Objectives
Success Criteria
Start Date: 15th September 2023 End Date: 20th September 2023 Allocated time: 4 days