2.3.5 Language Manager #76

Closed Joo-ooo closed 10 months ago

Joo-ooo commented 10 months ago

High Priority

To complete M2 Report section - Component Diagram

Objective

Draft and refine for component diagram related to Language Manager.

Success Criteria

All the facets (lollipop) and connectors must shown correctly in the diagram List out all the components used for the system.

Start Date: 9th October 2023 End Date: 20th October 2023 Allocated Time: 10 days

Cherlin01 commented 10 months ago

Image

Cherlin01 commented 10 months ago

Drafting and refining of Language Managment System for Components Diagram completed. The diagram is shown as above.

Work was not committed to the repository.

Progress does not affect the deadline.

No changes to the criteria/success of the task.

Start Date: 9th October 2023 End Date: 20th October 2023