2.4.1 Job Allocation #77

Closed Joo-ooo closed 10 months ago

Joo-ooo commented 10 months ago

High Priority

To complete M2 Report section - Sequence Diagram

Objective

Complete sequence diagram for Job Allocation based on the Use Case Description

Success Criteria

The diagram must follow the use case description The diagram must describe how the objects communicate with each other All flows must be shown in the diagram

Start Date: 23rd October 2023 End Date: 27th October 2023 Allocated Time: 5 days

Cherlin01 commented 10 months ago

Image

Cherlin01 commented 10 months ago

Creation of sequence diagram for Job Allocation completed. The sequence diagram is shown as above.

Work was not committed to the repository.

Progress does not affect the deadline.

No changes to the criteria/success of the task.

Start Date: 23rd October 2023 End Date: 27th October 2023