Issue Description

Current behavior Some calculations in previous reports do not line up with the expected costs, such as the wrong variables, the wrong value unit convergent, the wrong account number, etc.

Ganda, F., Maronati. G, Taiwo, T. A., and Kim, T. K. Report on Cost Estimation Algorithm for Advanced Nuclear Reactor Concepts. United States: N. p., 2017

Ganda, F., Taiwo, T. A., and Kim, T. K. Report on the Update of Fuel Cycle Cost Algorithms. United States: N. p., 2018

Ganda, F., Hoffman, E., Taiwo, T. A., Kim, T. K., and Hansen, J. Report on the ACCERT Cost Algorithms Tool. United States: N. p., 2019.

Hoffman, E., Abou-Jaoude, A., and Foss, A. Improvement of ACCERT Algorithm - FY20. United States: N. p., 2020.

Expected behavior/code Collect all the corrections needed.


For Issue Closure

This review should occur when the issue is going to be closed.

JiaZhou-PU commented 1 year ago

FY18

Page 9 Table 4 last row Source Year dollar CPI index factor Above inflation escalation factor Total escalation factor
(Holcomb 2011) 2011 1.10 0 1.10
Should be Source Year dollar CPI index factor Above inflation escalation factor Total escalation factor
(Holcomb 2011) 2011 1.10 1.0 1.10
JiaZhou-PU commented 1 year ago

FY18

Page 13 Figure 3 function should show as

y = 3.7012x^{0.4848}
JiaZhou-PU commented 1 year ago

FY18

Page 14 A function for the `Costing relation law for nuclear steam turbine' should have such form:

C_{turbine,eqp}= \frac{362.62}{n}
JiaZhou-PU commented 1 year ago

FY18

Page 17 Table 15

Interior structures Quantity labor hours Labor cost Material cost Unit labor cost Unit material costs Units
Reactor cavity liner plate 11000 SF 33,000 762,300 621,291 64.73 52.76 $/m2

This line should be removed from the table, since the cost is duplicated in Table 17

Others Quantity labor hours Labor cost Material cost Unit labor cost Unit material costs
Reactor cavity liner plate 11000 SF 33,000 762,300 621,291 745.94 607.96 $/m2

Item in Table 15 is normalized by Internal surface

2*V_{Internal}/t_{Intern, wall} = 11,775.80039m^2

item in Table 17 is normalized by Reactor cavity area:

11000ft^2 (1021.93344m^2)

It is suggested to keep the item in Table 17.

JiaZhou-PU commented 1 year ago

FY18

Page 23 Eq $C{226,7}=127.2 million \cdot(\frac{MW{th}}{3431})^{0.80}$ Should be

C_{226,7}=127.2 million\cdot (\frac{MW_{th}}{2287})^{0.80}

The scaled base should be 2287 MW rejected thermal power not thermal power 3431 MW.

JiaZhou-PU commented 1 year ago

Page 32 function for $C{226}$ should change to $C{213}$

JiaZhou-PU commented 1 year ago

FY18

Page 32 to 33 function should change to:

C_{235,eqp}=C_{231,fac}\cdot0.089 \\
C_{235,lab}=C_{231,lab}\cdot1.303 \\
C_{235,mat}=C_{231,mat}\cdot0.858 
JiaZhou-PU commented 1 year ago

FY18

Page 33 function for Electrical plant equipment should be:

C_{sum(245,246,242,241)}=213.8 million\cdot(\frac{MW_e}{1144})^{0.4}
JiaZhou-PU commented 1 year ago

FY18

The COA is wrong for some accounts, the correct ones are:

Reactor Primary Vessel \ 3.6.4 Expected Cost of the Primary Vessel of the Reference PWR12-BE(220A211)\ 3.6.5 Installation Cost (221.12)

Steam Generators \ 3.8.1 Factory Equipment Cost (220A.223)\ 3.8.2 Installation Cost (222.13)

Reactor Coolant Pumps and Drives \ 3.16.1 Factory Equipment Cost (220A221)

3.21 Lower and Upper Internals(220A2121,220A2122)

3.22 Control Rods (Account 220A2131) and Control Rods’ Drives (Account 220A2132)\ 3.22.1 Cost of Control Rods (Account 220A2131)\ 3.22.2 Cost of Control Rods Drives (Account 220A2132)

4.1.15 Auxiliary cooling system (226.7)

JiaZhou-PU commented 1 year ago

FY18

Page 67 4.1.9 Turbine Room and Heater Bay (Account 213) Function should be:

C_{\bm{213},fac}=1.8 million \cdot(\frac{1000 MW}{3431 MW})^{0.8} \\
C_{\bm{213},lab}=31.8 million \cdot(\frac{1000 MW}{3431 MW})^{0.8} \\
C_{\bm{213},mat}=32.4 million \cdot(\frac{1000 MW}{3431 MW})^{0.8} 
and the Table 63 should be Account Factory equipment Site labor Site material Total
213 Turbine room and heater bay building $0.7 million $12.0 million $12.2 million $24.8 million