Open Sparrow0hawk opened 7 months ago
Internal feedback:
Actual dates can be inputted as going backwards in time, so you can complete construction before you’ve actually started it etc.
Agree there needs to be a restriction that dates can only run chronologically through milestones.
Authority feedback:
We noticed that an error had occurred on the inputting of one of our dates (see below). We were a little surprised it was possible to enter a completion date that was actually earlier than a construction started date.
As an LA I want to ensure changed milestone dates have the correct chronology based on the order of milestones.
Acceptance criteria