Checklist for Temurin Release January 2024 #16

Closed Haroon-Khel closed 7 months ago

Haroon-Khel commented 8 months ago

This Temurin release checklist based on the release doc captures what activities must happen during a release.

The target release date is: 2024-01-16

The release champion for this release is: @Haroon-Khel

Planned absences during the release cycle:

The role of the release champion is to ensure that all release activities listed in this checklist get completed (by delegation to the broader team or by the release champion themselves). The final task of the release champion during a release is to confirm that all items in the checklist were completed satisfactorily and the release can be declared complete.

Everyone participating in a release, including the release champion are requested to provide feedback into the release retrospective so that the release process can be continuously improved (through simplification and/or automation).


Two Weeks Prior To Release

Ensure ALL nodes online prior to running these following TC steps:

One Week Prior To Release

After 1 day, then :-

Wait For All Of The Above To Complete Successfully Before Proceeding!


Release Week Checklist:

Release Day Onwards