Checklist for Temurin Release March 2024 #32

Closed steelhead31 closed 7 months ago

steelhead31 commented 8 months ago

NOTE: Items marked jdkxx and TEMPLATE_UPDATEME should be replaced while deploying this issue template. It is recommended to delete this line once you've done so :-)

This Temurin release checklist based on the release doc captures what activities must happen during a release.

The target release date is: 19th March 2024

The release champion for this release is: Scott Fryer

Planned absences during the release cycle:

The role of the release champion is to ensure that all release activities listed in this checklist get completed (by delegation to the broader team or by the release champion themselves). The final task of the release champion during a release is to confirm that all items in the checklist were completed satisfactorily and the release can be declared complete.

Everyone participating in a release, including the release champion are requested to provide feedback into the release retrospective so that the release process can be continuously improved (through simplification and/or automation).


Two Weeks Prior To Release

Ensure ALL nodes online prior to running these following TC steps:

ALL OK - Except jck-skytap-aix72-ppc64-3 which is clean, but had issues with git, issue logged with EF Infra https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/issues/4419 NOW RESOLVED

One Week Prior To Release

After 1 day, then :-

Wait For All Of The Above To Complete Successfully Before Proceeding!


Release Week Checklist:

Release Day Onwards

steelhead31 commented 8 months ago

Add new sections related to adding a new version to this checklist... 

1) Branch helper repo
2) Add TCK new version
3) Add ci-jenkins-pipeline release.groovy

smlambert commented 7 months ago

Think the only thing that remains is the update to the support page, fyi @sxa you can close this checklist issue after you are done with it

Update support page (automate* github workflow to create a PR to update support webpage) @sxa volunteered to do so, as he was also going to update to include RISC-V

steelhead31 commented 7 months ago

Release has been completed, so closing.