Closed afiqdanialll closed 11 months ago
Task Comments: Nil
Describe the work done in detail. Screens related to use case ALL1 and its related requirements set in M1 and M2 were created.
Has this work been committed to the repo? Yes
How does the work affect the completion deadline. Required for report writing and video demo
Are there any changes to the success or completion criteria of the task? If yes, please describe the details. No
Start and end date of the work done for this comment. 2-3 Nov 2023
Task details: To create the required screens for use case ALL1 in the prototype.
Task goals: To ensure required screens are created and is able to show the requirements as set in M1 and M2 and the ALL1 use case.
Success/completion criteria: When required screens are created and is able to show the requirements as set in M1 and M2 and the ALL1 use case.
Allocated time: 2 days
Start date: 2 Nov 2023
End date: 3 Nov 2023
Task owner: Afiq
Task status: Completed
Task priority: High