Describe the bug The time stamp of calendar events in the scheduled view do not respect clock format setting. They are always in 12-hour format.

To Reproduce Steps to reproduce the behavior:

  1. Make sure Calendar Events are enabled in Settings -> General
  2. Add event via GNOME Calendar with a time specified
  3. Look at the scheduled view in Planify

Expected behavior The time should be in 24-hour format if the user prefers this format in the settings.

Screenshots image

Desktop (please complete the following information):

golamrabbiazad commented 8 hours ago

The time stamp of calendar events in the scheduled view do not respect clock format setting. They are always in 12-hour format.

They are always in 12-hour format because you might have changed the clock format to 12-hour in settings. By default, the clock format is set to 24-hour.

Screenshot

Screenshot from 2024-09-26 20-54-01

To change the clock format, Follow the step,

  1. Preferences
  2. General
  3. Date and Time
  4. Clock Format
majjejjam commented 8 hours ago

I have not changed the setting. The times in the scheduled are displayed as 12-hour even though the setting is configured to be 24-hour.

image

I don't know if this affects anything, but I also have 24-hour in GNOME Settings: