Use the new Cost Control section to enable currencies and budgeting in Kanboard. Get live currency rates automatically for over 120 currencies allowing users to compare with manually saved rates. This plugin replaces and extends the features from the original Budget plugin enabling projects to have an associated cost element.
MIT License
4
stars
1
forks
source link
CostControl based on static costs assigned to tasks #11
I'm using this plugin to manage an event. So in this case we have static costs wich comes from our contractors / invoices.
I can set budget line but how to set costs to tasks?
So the my question is it possible (if yes please give me a hint).
How to set task cost when eg. its moved to DONE (or just set to each item whereever exist in column).
Then in chart display:
budget
costs which are pending - task IN PROGESS
costs which are confirmed - task DONE
I know maybe these are my wishes but give a hint its possible :) or some support (private message) to add this feature :D
Hi!
I'm using this plugin to manage an event. So in this case we have static costs wich comes from our contractors / invoices.
I can set budget line but how to set costs to tasks?
So the my question is it possible (if yes please give me a hint). How to set task cost when eg. its moved to DONE (or just set to each item whereever exist in column).
Then in chart display:
I know maybe these are my wishes but give a hint its possible :) or some support (private message) to add this feature :D