We should decide upon a fixed timeline to start and finish off the coding. Our 
first working model of the system is due on OCTOBER 17, so we should keep a 
buffer of 2 weeks. So our internal deadline is OCTOBER 3. Can we utilize the 
recess week and schedule 3 meetings of 2 hours duration where we can meet and 
code together? I would propose Tuesday, Thursday and Friday 4-6 pm in PGP? In 
addition, we can work on our individual responsibilities at our own 
convenience. 

Original issue reported on code.google.com by supersa...@gmail.com on 19 Sep 2012 at 10:37

GoogleCodeExporter commented 8 years ago
I agree :)

Original comment by akaash.g...@gmail.com on 20 Sep 2012 at 3:10