Project Support
[x] OpenDRIVE 1.8 - supporting PL (including meeting slot coordination via the new
project-office@asam.net
email)
[x] Initial setup new project-office account incl. OpenXCalendar
Review of OpenODD & OpenDRIVE/CityGML proposals
[x] Work with the ASAM office to review and finalise the overall project proposal - postponed
[x] Read proposal and identify gaps (OpenDRIVE/CityGML)
[x] Ensure these are filled by the proposal team
[x] Ensure proposal writers define a realistic and sufficiently project plan - postponed
Project Guide
[x] (shifted from April) Finalise role definitions and expectations towards an ASAM PL
comment:
Done on 03.05.2022 with
commit/37092b71e02ddd1aa76e7eb00cff1e008a9c0a21
Additional Topics (not written in initial document)
[x] Setting up new labels for OpenDRIVE (for possible rollout on all repositories)
florianwallerer
commented
2 years ago
Project Support
OpenDRIVE 1.8 - supporting PL (including meeting slot coordination via the new
project-office@asam.net
email) - ongoing
The cooperation and exchange with OpenDRIVE PL has started well and is working out great
A new MiroBoard structure and new MiroBoards were created at the PL's request -
Done
The revision of the new OpenDRIVE Timeline -
Done
Milestone TSC März 2023
Milestone Document Freeze 2 weeks before
Keep in mind: 1 week before document freeze, prepare documents
2 weeks to implement review tasks, after internal review of documents
Reorder sections
No need for a public review (ASAM office)
Talk to PL about: Workpackages shall not be longer than 3 Months and shall end with a milestone -
OPEN
Initial setup new project-office account incl. OpenXCalendar -
Done
florianwallerer
commented
2 years ago
Review of OpenODD & OpenDRIVE/CityGML proposals
Work with the ASAM office to review and finalise the overall project proposal
Read proposal and identify gaps (OpenDRIVE/CityGML) - done
We have only received the OpenDRIVE/CityGML proposal, the other one has arrived on 2022/05/24.
Read proposal and identify gaps OpenODD - ongoing
Work on Proposal started on 2022/05/30 due to arrival of the proposal (2022/05/24) and vacation.
Work is ongoing. Need maybe 2/3 more days.
Ensure these are filled by the proposal team
ASAM Office had a first discussion on the proposal with the new comments. The team will work on them.
Ensure proposal writers define a realistic and sufficiently project plan
florianwallerer
commented
2 years ago
Project Guide
(shifted from April) Finalise role definitions and expectations towards an ASAM PL
Done on 03.05.2022 with
commit/37092b71e02ddd1aa76e7eb00cff1e008a9c0a21
florianwallerer
commented
2 years ago
Additional Topics (not written in initial document)
Setting up new labels for OpenDRIVE (for possible rollout on all repositories) -
Done
Documentation of new labels -
OPEN
Project Support
Review of OpenODD & OpenDRIVE/CityGML proposals
Project Guide
Additional Topics (not written in initial document)