Team,

I'm looking for a feature in the Gantt Chart where, I can accomodate along with 
the Start date and End date, I also want to track the start date + start time 
of that day, and then end date + end time of that day to be more precise.

Can you please help on how to achieve this?

Thanks,
Shabin.

Original issue reported on code.google.com by rsha...@gmail.com on 10 Nov 2014 at 7:02

GoogleCodeExporter commented 9 years ago
Sorry, but I can't say that I understand the question. Please rephrase it 
somehow.

Original comment by dbaras...@ganttproject.biz on 12 Nov 2014 at 10:00

GoogleCodeExporter commented 9 years ago

Original comment by dbaras...@ganttproject.biz on 12 Nov 2014 at 10:05

GoogleCodeExporter commented 9 years ago
I need to track a specific project that span to hours like the maintenance 
window of a datacenter, which is time specific rather than a big project that 
is days in terms of the measurement of the span of the project.

Certain activities needs to be preciously measured with date + timestamp (for 
the start of the activities) and then the corresponding date + timestam (for 
the end of the activities) needs to be measured.

Is it possible in this tool?

Let me know if it is clear. 

Original comment by rsha...@gmail.com on 13 Nov 2014 at 12:12

GoogleCodeExporter commented 9 years ago
Hours are not supported, sorry. See 
http://ganttproject.blogspot.ru/search/label/faq

Original comment by dbaras...@ganttproject.biz on 13 Nov 2014 at 12:15