Closed GoogleCodeExporter closed 9 years ago
What do you mean when you say "won't allow me to do so"? Every new task is
created with duration 1 day and thus it starts and ends on the same day.
Doesn't it work for you?
Weekends in GP 2.6 are all-or-nothing: you can either have all weekends working
(you can choose to show weekend days, though) or all weekends non-working.
GP 2.7 supports weekend exceptions, see http://www.ganttproject.biz/ostrava
Original comment by dbaras...@ganttproject.biz
on 12 Nov 2014 at 5:41
Thanks for such a prompt reply. What I mean is, even when I type in the
specific end date, it changes to the next date. How do I choose to show
weekend days?
Original comment by pldesgro...@gmail.com
on 12 Nov 2014 at 6:33
Can you record a screencast showing how do you change dates?
Calendar can be configured in
Project->Properties->Calendar
Original comment by dbaras...@ganttproject.biz
on 12 Nov 2014 at 7:11
Original comment by dbaras...@ganttproject.biz
on 24 Nov 2014 at 10:54
Original issue reported on code.google.com by
pldesgro...@gmail.com
on 12 Nov 2014 at 5:35