Dear,

I want to task to begin and end on the same day and it won't allow me to do so. 
 Also, I want to use weekend dates on some parts of the chart

Original issue reported on code.google.com by pldesgro...@gmail.com on 12 Nov 2014 at 5:35

GoogleCodeExporter commented 9 years ago
What do you mean when you say "won't allow me to do so"? Every new task is 
created with duration 1 day and thus it starts and ends on the same day. 
Doesn't it work for you?

Weekends in GP 2.6 are all-or-nothing: you can either have all weekends working 
(you can choose to show weekend days, though) or all weekends non-working. 

GP 2.7 supports weekend exceptions, see http://www.ganttproject.biz/ostrava

Original comment by dbaras...@ganttproject.biz on 12 Nov 2014 at 5:41

GoogleCodeExporter commented 9 years ago
Thanks for such a prompt reply.  What I mean is, even when I type in the
specific end date, it changes to the next date.  How do I choose to show
weekend days?

Original comment by pldesgro...@gmail.com on 12 Nov 2014 at 6:33

GoogleCodeExporter commented 9 years ago
Can you record a screencast showing how do you change dates? 

Calendar can be configured in
Project->Properties->Calendar

Original comment by dbaras...@ganttproject.biz on 12 Nov 2014 at 7:11

GoogleCodeExporter commented 9 years ago

Original comment by dbaras...@ganttproject.biz on 24 Nov 2014 at 10:54