Change holiday does not adjust dependent tasks #1080

Closed GoogleCodeExporter closed 9 years ago

GoogleCodeExporter commented 9 years ago
What steps will reproduce the problem?
1.Create a set of tasks that are sequentially dependent on each other.
2.Change a day within a task to a holiday.  Observe dependent tasks do not time 
ripple.
3.Save and reload.  The dependent tasks are now adjusted properly.

What is the expected output? What do you see instead?
When the holdiay is added then any event spanning the holiday is adjusted, but 
dependent tasks do not move until the project is saved and reloaded.

What version of the product are you using? On what operating system?
2.7 build 1891 on Windows 

Please provide any additional information below.

Original issue reported on code.google.com by kurtbutf...@gmail.com on 11 Feb 2015 at 10:51

Attachments:

GoogleCodeExporter commented 9 years ago
I should also note that removing a holiday has similar behavior.

Original comment by kurtbutf...@gmail.com on 11 Feb 2015 at 10:52

GoogleCodeExporter commented 9 years ago
Thanks for reporting. It is not necessary to save and reload project. It is 
enough to touch the end date of any task (not necessarily crossing the added 
holiday, just any)

Original comment by dbaras...@ganttproject.biz on 11 Feb 2015 at 10:57

GoogleCodeExporter commented 9 years ago
This issue was closed by revision 9dc7433b0549.

Original comment by dbarashev on 18 Jun 2015 at 8:54