Support planned dates vs actual dates #591

Open GoogleCodeExporter opened 9 years ago

GoogleCodeExporter commented 9 years ago
Each task should have those additional atributes as almost "always"
planned start and finish times differe from real ones.

So when the project is delayed the delay should be marked as a line or symbol 
within current project.

Original issue reported on code.google.com by dpba...@gmail.com on 21 Sep 2012 at 10:40

GoogleCodeExporter commented 9 years ago

Original comment by dbarashev on 21 Sep 2012 at 10:50

GoogleCodeExporter commented 9 years ago
the above mentioned feature should be added to both Gant and Resources Chart

Original comment by dpba...@gmail.com on 11 Oct 2012 at 7:15

GoogleCodeExporter commented 9 years ago
Task is started 01.03.2013 and end date is 12.03.2013 but is not completed 
between this date. So progression must will going to actual end date. This task 
actual end date may 20.03.2013. So task is 8 days late for this example. How 
can I get this event progressions.

Default end date is(planning) so I need to actual end date for some tasks. Is 
it possible?

Thank you, Regards...

Original comment by hasanon...@gmail.com on 19 Mar 2013 at 8:09

GoogleCodeExporter commented 9 years ago
Issue 782 has been merged into this issue.

Original comment by dbarashev on 7 May 2013 at 10:25

GoogleCodeExporter commented 9 years ago
Issue 782 has been merged into this issue.

Original comment by dbaras...@ganttproject.biz on 10 Aug 2014 at 6:50