PERT Chart dates wrong. #819

Closed GoogleCodeExporter closed 9 years ago

GoogleCodeExporter commented 9 years ago
What steps will reproduce the problem?

I am studying project management and almost lost a few marks as you can see the 
start date of review records may not be the same as end date of Conduct series. 
If a task ends on day 3 the next task can start on day 4 not on the same day. 
The dates are correct under the Gantt chart but differs on the PERT chart.

I may need to look for a different program until this is fixed to submit my 
assignment.

What is the expected output? What do you see instead?

The predecessor task dates may not be the same as current task. It should be a 
day after the task ended.

What version of the product are you using? On what operating system?

Mac OS X 10.8.4 using the version GanttProject 2.6.1

Please provide any additional information below.

Original issue reported on code.google.com by djdaf...@gmail.com on 31 Jul 2013 at 7:45

Attachments:

GoogleCodeExporter commented 9 years ago

Original comment by dbarashev on 10 Feb 2014 at 10:51

GoogleCodeExporter commented 9 years ago

Original comment by dbarashev on 2 Sep 2014 at 8:30

GoogleCodeExporter commented 9 years ago
This issue was closed by revision d5a8f2338d50.

Original comment by dbarashev on 2 Sep 2014 at 8:30

GoogleCodeExporter commented 9 years ago

Original comment by dbaras...@ganttproject.biz on 11 Nov 2014 at 10:36

GoogleCodeExporter commented 9 years ago
Closing all tickets with status "FeelFreeToTest". Feel free to reopen if the 
issue is still reproducible.

Original comment by dbaras...@ganttproject.biz on 18 Mar 2015 at 3:39