Closed GoogleCodeExporter closed 9 years ago
Thanks for reporting, I'll have a look.
Original comment by dbarashev
on 16 Feb 2014 at 11:49
I've looked very quickly and my impression is that it is working as intended.
By definition, a task is critical if its float is zero (that it, it can't be
delayed without increasing the whole project duration). In your project, even
the task which is the last in the chain (task #172, "Tutorial day") has a
single predecessor with 3 days lag, so the whole preceding chain can be delayed
with no impact on the project end date.
GanttProject highlights two summary tasks as critical: "BSBWHS501A – Ensure a
Safe Workplace" and "Diploma of Management" -- they really have no float.
Unfortunately the highlighting is barely visible (only endings of the task bar
become red)
Original comment by dbarashev
on 16 Feb 2014 at 12:03
Original comment by dbarashev
on 26 Feb 2014 at 8:20
Original issue reported on code.google.com by
Scott.Wo...@gmail.com
on 16 Feb 2014 at 11:19Attachments: