this is an other issue (enhancement) to use a global calendar and optional per resource/resource category calendar.
current calendar of a space remains default
manager can create calendar objects (identical fields to current default one)
manager can assign resources to a calendar
calendar has an option to be independent or shared between resources, each assigned resource bookings are independent else on booking we check they do not overlap between resources using this calendar
when a resource is assigned to a calendar, if was already assigned to an other one, assign to new one
calendar view should show assigned resources
calendar view should show "unassigned" resources (using default)
on invoice, if resource is linked to a calendar, use this calendar for weekend/night/... calculation
on booking if resource is linked to a calendar:
Multiple calendar system should be flagged so that could be assigned per space plan (if plan do not have flag, just show/use default calendar)
Future enhancement idea: add per calendar closing days/hours (start/end timestamp) that would appear in calendar view as closed and checked for conflicts on booking (rather than adding fake bookings)
Use case raised by H2P2 : Depending on which resource is booked, constraints on schedules are not the same. An enhancement would be to integrate the possibility to set a specific schedule for a specific resource.