Closed egemenatikk closed 1 year ago
I reviewed the requirements and created the part that is related to making a report on the progression according to the requirements. I wrote all frontend related and most of the backend related progress.
I reviewed the requirements and filled the rest of the related part in the general group report for milestone 2. I filled all mobile related progress and remaining backend progress.
Issue Description
For our second milestone report, we are asked to review our progress according to our requirements. After revision of our requirements is completed, @egemenatikk and @gokayyildiz will review our project's progress according to our requirements in terms of front-end part, back-end part and mobile part.
Step Details
Steps that will be performed:
Final Actions
After this task is completed and approved by the reviewer, this issue will be closed and related part will be added to our group's second milestone report.
Responsible People
Deadline of the Issue
09.12.2022 - Friday - 15:00
Reviewer
Ecenur Sezer
Deadline for the Review
09.12.2022 - Friday - 16:00
Final To-Dos