An issues-only repository for the Bryntum project management component suite which includes powerful Grid, Scheduler, Calendar, Kanban Task Board and Gantt chart components all built in pure JS / CSS / TypeScript
Plan de coaching y seguimiento a iniciativas estrat?gicas 2021 task should start 2021-03-16 8:30:0 because of non working third Monday of March rule. But the rule is not imported.
MS Project importer doesn't process project calendar recurring exceptions properly.
Reported here: https://www.bryntum.com/forum/viewtopic.php?f=52&t=17556 File to reproduce: Gantt_Import_Dates_Issue.zip
Plan de coaching y seguimiento a iniciativas estrat?gicas 2021
task should start2021-03-16 8:30:0
because of non workingthird Monday of March
rule. But the rule is not imported.