on new exception there the current date is set as start, the end to one day later. If you enter first the start to a future date and then the end, the start on saving the calendar is set back to the current date. Also the end date is not included (what you normally would expect)
Forum post
on new exception there the current date is set as start, the end to one day later. If you enter first the start to a future date and then the end, the start on saving the calendar is set back to the current date. Also the end date is not included (what you normally would expect)