An issues-only repository for the Bryntum project management component suite which includes powerful Grid, Scheduler, Calendar, Kanban Task Board and Gantt chart components all built in pure JS / CSS / TypeScript
Hi,
I see that this ticket has already been resolved since version 6.0.2 but the problem persists. When importing the file (Bryntum Example.mpp) that I attached at the beginning of this ticket, the start and end dates of the project do't match.
It seems that you are not taking into account the project calendar, in Bryntum Gantt it assumes that April 4th to April 21st are 46 days, this is not correct.
Please help us with this ticket, we need to go into production and this error prevents it.
Forum post
Hi, I see that this ticket has already been resolved since version 6.0.2 but the problem persists. When importing the file (Bryntum Example.mpp) that I attached at the beginning of this ticket, the start and end dates of the project do't match.
It seems that you are not taking into account the project calendar, in Bryntum Gantt it assumes that April 4th to April 21st are 46 days, this is not correct.
Please help us with this ticket, we need to go into production and this error prevents it.
Bryntum Example.zip