I use Taskblocks primarily for impact analysis, by which I mean demonstrating
what the impact of a project would be if a new task is introduced (scope
creep). More usually, I have a raft of different projects in taskblocks and
wish to show the impact or introducing a new project.
It would be useful, after swapping and changing tasks (projects) around, to
roll back to the baseline.
As long as no-one presses "save" during the planning meeting, I can close the
App and open it again, but once "save" is pressed, I have lost my original plan.
Original issue reported on code.google.com by the.razm...@gmail.com on 22 Mar 2011 at 2:12