The project was available on time for review. The project obvectives are clear and an appropriate amount of progress was made, on track with the teams design.

Classes for the project are designed at appropriate sizes and serve a purpose. They are organized appropriately but contain some syntax errors leftover from applying code from class examples. I resolved some syntax errors that I found, but as the team finalizes the project I do not believe they will have any trouble.

The UI layers are separated appropriately. The project has several build errors and I was not able to see a live web page of the project, but based on what I saw from sprint 1, they have been implementing their database appropriately and should be able to compile the project after database implementation is completed. There are no empy catches or exceptions found in the project.