Description

In order to transition from a bi-project development cycle into a centralized Development Board, we need to add new meaningful custom fields.

Possible Solution(s)

A clear and concise description of what you want to happen.

Objectives

Please specify what the finished feature should accomplish (one or more objectives):

Additional Context

Current custom fields for the Development Board image

fjbo-net commented 6 months ago

Blocks:

fjbo-net commented 6 months ago

Blocks:

fjbo-net commented 6 months ago

Blocks:

fjbo-net commented 6 months ago

Custom field "Status" has been updated to issue objectives:

image

fjbo-net commented 6 months ago

Custom field "Priority" has been updated to fulfill issue's objectives:

image

fjbo-net commented 6 months ago

Custom field "Size" is already up to issue's objectives:

image

Added an understandable definition for each size:

image

fjbo-net commented 6 months ago

Custom field "Category" is up to issue's objectives:

image

No changes needed.

fjbo-net commented 6 months ago

Added new custom field "Target Date":

image

fjbo-net commented 6 months ago

Added new custom field "Start Date":

image

fjbo-net commented 6 months ago

An iteration field cannot be set to the original creation of the Cotheca Project. Reviewing the previous sprints, I have concluded that naming does not overlap. Previously, Cotheca had 24 sprints in a year, and the sprint was approximately to 2-weeks. However, it was calendar-based starting the first sprint of any given month on the 1st of the month, and the 2nd sprint starting on the 16th of the month.

Going with a new numbering system starting on next Monday (04-29-2024) will make more sense as it's a new iteration system and does not reference the previous iteration system.

The new custom field "Sprint" has been created:

image

Five (planned) sprints have been added to cover 2024 Q2.

fjbo-net commented 6 months ago