Subject: feedback on week 6 project progress

See v1.1 progress guide for more details of the activities mentioned below.

Team progress

Individual progress of @beesaycheese

Individual progress of @whyjayxp

Individual progress of @qing-yuan

Individual progress of @bava98

Tutor: @marlenekoh

Note: the above observation was done by the CS2103-feedback-bot and covers changes up to 2019-02-20 00:00:00 only. If you think the above observation is incorrect, please let us know by replying in this thread. Please include links to relevant PRs/comments in your response.

beesaycheese commented 5 years ago

@marlenekoh Hi Marlene, we realised that the bot did not tick "PRs created to update documents". Actually, we did accomplish this milestone last week. However, we did so by editing the contents directly on to the main. This was done during one of our meetings, where all of us were present to give consent to the changes made. Hence, there was no need for us to pull request. May we, therefore, request for you to take note that we have actually finish our milestone please? Thank you!

marlenekoh commented 5 years ago

@beesaycheese Noted (: Will take a look, thank you!

@marlenekoh Hi Marlene, we realised that the bot did not tick "PRs created to update documents". Actually, we did accomplish this milestone last week. However, we did so by editing the contents directly on to the main. This was done during one of our meetings, where all of us were present to give consent to the changes made. Hence, there was no need for us to pull request. May we, therefore, request for you to take note that we have actually finish our milestone please? Thank you!

okkhoy commented 5 years ago

We want you to follow the workflow properly at least until the first couple of milestones. Hence the bot is configured to check for PRs. Since there was no PR for documentation, the bot has rightly identified it so.

No much damage done; we want you to achieve only 60% of the project management tasks, so you have a lot of leeway.

For v1.1 please ensure that you have a PR for some documentation changes.