Activity Dates and Status #64

Open rbesseling opened 4 years ago

rbesseling commented 4 years ago

Missing Rule:

Activity needs at least an Planned / Actual End Date

Missing Rule:

Activity Status cannot be Finalisation if no Planned / Actual End Date is present

Missing Rule:

If activity date has ended, Activity Status should not be Implementing

PetyaKangalova commented 4 years ago

@rbesseling thanks for all your feedback so far :)

None of the rules you have listed above are rules in the standard at the moment so hence they have not been incorporated at the moment : http://reference.iatistandard.org/203/activity-standard/iati-activities/iati-activity/activity-date/

I know that there has been discussion on this on IATI discuss, so I am putting this as enhancement for discussion.

rbesseling commented 4 years ago

Time for some commonsense rules :-)